Nachtigal hydropower plant: a significant step forward for Cameroon’s energy sector
March 2025 – September 2025: the 7 units of the Nachtigal plant have now been in service for 6 months. With an installed capacity of 420 MW, Nachtigal is today Cameroon’s largest electricity producer.
The dam, built and operated by Nachtigal Hydro Power Company (NHPC), alone supplies nearly 30 % of the country’s electricity needs, rightly making it the driving force behind Cameroon’s energy growth.
Since commissioning began in June 2024, the Nachtigal hydropower plant has already fed more than 2 TWh of electricity into the national grid and is strengthening the available energy supply, supporting the balance of Cameroon’s power system.
- 07
- turbines
- 420 MW
- of installed capacity
- ≈ 30 %
- of Cameroon’s electricity needs covered
- 35 years
- operating concession granted to NHPC
Satisfactory results on several fronts
This performance is the result of a combination of key success factors on which the Nachtigal project builds, including:
- Reliability. Since commissioning, the plant has operated reliably and steadily, thanks to robust equipment and a rigorous preventive maintenance strategy. Very few technical incidents have been recorded so far, and those that have remained well below contractual thresholds and international standards for hydropower operation. Each situation is handled quickly and efficiently by the operating teams, ensuring continuity of service.
- Health, safety and dam safety. Since commissioning, the plant has recorded no serious accident and no significant dam safety event. This result reflects the constant vigilance and professionalism of the operating teams.
- Reliance on local skills. The plant is operated by a team of young Cameroonians, trained to national and international standards, who run the facilities rigorously every day.
Started on 1st February 2019, construction work at Nachtigal was completed with the commissioning of the 7th unit in March 2025. The units were commissioned in stages between June 2024 and March 2025. This approach allowed the generating units to be integrated gradually and rigorously into the existing power grid. Since August 2025, 420 MW are now supplied to the grid every day, especially at peak hours, to guarantee an optimal electricity supply to Cameroonians.
Key dates
- NHPC is incorporated as a public limited company under Cameroonian law
- Construction of the Nachtigal hydropower plant begins
- Unit 1 commissioned (60 MW)
- Unit 2 commissioned (60 MW)
- Unit 3 commissioned (60 MW)
- Unit 4 commissioned (60 MW)
- Unit 5 commissioned (60 MW)
- Unit 6 commissioned (60 MW)
- 1st TWh reached
- Unit 7 commissioned (60 MW)
- Final commissioning of the Nachtigal hydropower plant
- 2th TWh reached
Seamless synergy for national benefit
Nachtigal’s success is the fruit of exemplary collaboration. NHPC works in close synergy with the main players in the power sector:
- ENEO, the distributor, for optimal electricity distribution;
- SONATREL, the transmission operator, to carry power across the country;
- EDC, the water management company, to optimise the use of the water resource, namely the Sanaga River;
- ARSEL, the electricity sector regulator, under the authority of MINEE.
Thanks to all these entities, Cameroon now has, through the Nachtigal plant, clean, sustainable and competitive energy serving the country’s economic growth.
About NHPC
Incorporated on 7 July 2016, Nachtigal Hydro Power Company (NHPC) is a public limited company under Cameroonian law. It built and operates the Nachtigal hydropower plant (420 MW) on the Sanaga River under a 35-year concession.