Technical components
The construction of the Nachtigal project was divided into 4 main lots:
The construction works of the Nachtigal project have stared on February 1st 2019.
At the end of January 2025, the project’s overall progress rate was 98.3%, distributed as follows:
Civil engineering
0%
Electromechanical
0%
Transmission line
0%
Nachtigal Camp
0%